Construction Jobsite Delay Cost Calculator

Translate jobsite delay into actual project-cost exposure by separating critical-path days from float, then pricing overhead, standby, productivity, financing and damages.

Simple delay event

Separate calendar delay from true critical-path exposure

Float & Concurrency Gate
Delay logicCritical-path delay is calendar delay less available float and concurrent/overlapping delay, floored at zero. Daily delay costs apply only to those exposed critical-path days. Productivity loss, working-capital carry, one-time restart cost and liquidated damages are then added separately. Recoverability affects how much of the delay cost is expected to be reimbursed, not whether the cost occurred.
Delay Cost Stack

Where the delay cost comes from

Simple scenario
Duration sensitivity

Cost as critical-path exposure grows

Critical-path delayGross delay costExpected recoverableNet contractor exposureCost / critical day